• 全部
主办单位:煤炭科学研究总院有限公司、中国煤炭学会学术期刊工作委员会
大湾煤矿通风系统特征及通风能力核定
  • Title

    Features of Ventilation System in Dawan Mine and Ventilation Capacity Approved

  • 作者

    谢雄刚周林锋胡鲤庭李乾坤

  • 单位

    贵州大学矿业学院贵州大学瓦斯灾害防治与煤层气开发研究所贵州水城矿业(集团)有限责任公司大湾煤矿

  • 摘要
    选定矿井通风系统相对稳定的时期为核定时期,通过矿井需要风量计算,确定各采掘工作面、硐室及备用工作面的需风量;根据矿井通风能力计算,确定大湾煤矿合理的采掘比为1∶4,矿井通风能力为130万t,矿井等积孔3.97 m2,矿井为通风容易矿井。并从矿井通风动力、用风地点有效风量、矿井通风网络能力、稀释瓦斯能力等方面验证了矿井通风能力为130万t。井下各用风地点风流稳定,风量、风速、风阻满足要求,矿井通风网络能力能够满足安全生产的要求。
  • Abstract
    With the selected the relative stable period of the mine ventilation system as an approved period and with the calculation of the mine required ventilatio n, the required ventilation quantity of each mining and excavation working face, chamber and standby working face could be set up.According to the calculation of the m ine ventilation capacity, the rational mining and excavation ratio of Dawan Mine was 1 : 4, the mine ventilation capacity was 1 .30 million tons, the mine equivalent hole was 3.97 m2 and the mine was a easy ventilation mine.From the mine ventilation dynamics, the effective ventilation quantity at the ventilation location, the mine ventilat ion network capacity, gas diluted capacity and other aspect, the mine ventilation capacity was verified as 1.30 million tons.At the each ventilation location, the air flow w as stable and the ventilation quantity, air velocity and air resistance could meet the requirements. The mine ventilation network capacity could meet the requirements of t he production and safety.
  • 关键词

    通风系统需风量采掘比等积孔矿井通风能力

  • KeyWords

    ventilation system;required ventilation quantity;mining and excavation ratio;equivalent hole;mine ventilation capacity;

  • 基金项目(Foundation)
    贵州大学教育教学改革研究资助项目(gdjg[2010]032);贵州大学引进人才科研基金资助项目(贵大人基合字[2010]002号);贵州省教育厅自然科学重点资助项目(黔教科[2011]034号);贵州省国际科技合作计划资助项目(黔科合外G字[2009]700111号);
相关问题
立即提问

主办单位:煤炭科学研究总院有限公司 中国煤炭学会学术期刊工作委员会

©版权所有2015 煤炭科学研究总院有限公司 地址:北京市朝阳区和平里青年沟东路煤炭大厦 邮编:100013
京ICP备05086979号-16  技术支持:云智互联
Baidu
map